December Repave Telegraph Update

The contractor started installing cat-tracking on Friday, December 18th to mark the parking types. The City is reviewing and approving the cat tracking this week.
 
Repave Telegraph Update! The contractor started installing cat-tracking on Friday, December 18th to mark the parking types (yellow, green, etc). The City is reviewing and approving the cat tracking this week (Dec 21-24) and the contractor plans to install the paint to mark parking types AND delineate the pedestrian plaza before December 31, 2020. ⁠

Also, the City is working to fill a large cavity discovered under the sidewalk at 5020 Telegraph Ave. They have started investigative work to finalize how they plan to fix it, and have temporarily blocked off the pedestrian access at that location while the sidewalk is opened up. To fix the cavity, the City will create a concrete retaining wall below ground, next to the adjacent building, backfill the cavity with dirt, and then install a new sidewalk section on top. The work is estimated to take 2-3 weeks.⁠