The final top coat of asphalt is being installed on Telegraph Ave, with expected completion of this Phase 2 of 3 in the repaving construction plan, by June 26th. At the completion of Phase 2, temporary lane markers will be installed on the street (delineating the current lanes, not the finalized street design). After the completion of the new asphalt installation, the contractors will construct seven bus boarding islands along Telegraph, at West MacArthur, 40th St, 45th St., and 51st St.