Repave Telegraph Update – November 12
Repave Construction Update – October 26
Installation of the striping on Telegraph from 51st to above 52nd is ongoing. The green bike lane and red bus-only lane on Northbound Telegraph between 51st and 52nd was painted yesterday.
Repave Update
Permanent Striping and Bollards Installed on Telegraph
The permanent striping and K-71 bollards have been installed on Telegraph from 37th to 51st St! The temporary cat tracking on Telegraph from 51st to above 52nd is still being reviewed by the City.
Permanent Striping to be Installed Week of July 27
The cat tracking on Telegraph from 37th to 43rd has been approved, and the week of July 27th (this week), the contractor will install the permanent striping on that section starting at 37th St.
All Layers of Asphalt Installed on Telegraph Ave
All layers of asphalt have been on installed on Telegraph Ave. Last week, the contractor installed temporary cat tracking to mark the exact locations for permanent striping.